Project overview*

EIS status EIS active
Description Greenfield metallurgical coal mine with a yield of up to 8 million tonnes of product coal for approximately 30 years, for steel production.
Proponent Whitehaven WS Pty Ltd, a wholly owned subsidiary of Whitehaven Coal
Location/s Approximately 30 km south-east of Moranbah. Map
Local government/s Isaac Regional Council
Investment $1 billion
Key features
  • open-cut metallurgical coal mine
  • mine infrastructure areas including workshops and a coal handling and preparation plant
  • rail loop and train load out facility
  • private access road
  • raw water pipeline connecting to the Eungella pipeline network
  • electricity transmission line from the existing power network
  • on-site temporary construction accommodation camp
Construction start date 2021
Jobs
  • 500 (construction)
  • 450 (operational)

* Project information supplied by proponent and subject to change.

Environmental impact statement (EIS) process

Date Activity
17 and 18 July 2019

Commonwealth Minister for the Environment decided the project is a 'controlled action'.

More information

Currently Draft terms of reference for EIS and comments being assessed.
24 June 2019 to 19 July 2019 Public consultation period on draft terms of reference (PDF icon1.2 MB).
14 May 2019 Project referred to Commonwealth Minister for the Environment.
17 April 2019 Gazettal (PDF icon 247 KB) of ‘coordinated project’ declaration.
14 February 2019 Application, including initial advice statement (PDF icon 8.8 MB), submitted.

Media releases

$1 billion Winchester South project out for public comment (24 June 2019)

Economic boost for regional QLD with $1b Winchester South project declared (18 April 2019)

Further information

Read more about the EIS process.