The Department of State Development, Infrastructure, Local Government and Planning is changing to the Department of State Development and Infrastructure. Work is underway to update this website. Read more about the new Ministerial portfolios. Access Planning and Local Government content as changes are being progressed.

Skip to content

Central Queensland Gas Pipeline

Project overview*

EIS status Approved with conditions
Description A 450-kilometre, underground, high-pressure gas transmission pipeline from the Bowen Basin to Gladstone.
Proponent Central Queensland Pipeline Pty Ltd
Location/s Between Moranbah and Gladstone. Map
Local government/s
  • Gladstone Regional Council
  • Isaac Regional Council
  • Rockhampton Regional Council
Key features
  • 30-metre-wide easement
  • 300mm- to 400mm-diametre pipeline, buried at a depth of at least 900mm

* Project information supplied by proponent and subject to change.

Key environment impact statement (EIS) documents

EIS process

Read more about the EIS process.

Australian Government approval

Commonwealth Minister for the Environment's approval of controlled action, subject to conditions.

More information

Last updated: 09 Nov 2021